Project programme: design to handover in 30 months
The whole project on one page: phases, overlaps, the critical path and the milestones your payments, sales and financing are tied to.
Dark green = critical path. A delay on any dark bar moves handover.
Milestones
| Month | Milestone |
|---|---|
| M2 | Concept approved by client |
| M4 | Building permit; off-plan launch |
| M6 | Main contractor mobilised |
| M12 | Podium complete |
| M20 | Structure topped out |
| M28 | Building completion certificate |
| M30 | Handover to buyers |
What we track every week
- Planned vs actual progress by floor and by trade
- Look-ahead of materials and approvals needed in the next 6 weeks
- Cash: certified work, escrow releases, collections from buyers
Biggest schedule risks
- Authority approvals in months 2–4
- Long-lead items: lifts, chillers, façade (ordered by month 8)
- Labour availability during peak finishing (months 20–26)
Want this for your own project?
Tell us about it and the Projects team will prepare yours.
Illustrative sample for a fictional project. Figures are indicative only and are not an offer, valuation or professional advice. Your own study uses your plot, your market data and current rates, confirmed by Mizo's team.