Project programme: design to handover in 30 months

The whole project on one page: phases, overlaps, the critical path and the milestones your payments, sales and financing are tied to.

M0M3M6M9M12M15M18M21M24M27M30Concept and schematic designDetailed design and approvalsOff-plan launch and salesMain contract tenderEnabling works and pilingSubstructure and podiumSuperstructure (12 floors)Envelope and façadeMEP installationFit-out and finishesTesting and commissioningCompletion and handover

Dark green = critical path. A delay on any dark bar moves handover.

Milestones

MonthMilestone
M2Concept approved by client
M4Building permit; off-plan launch
M6Main contractor mobilised
M12Podium complete
M20Structure topped out
M28Building completion certificate
M30Handover to buyers

What we track every week

  • Planned vs actual progress by floor and by trade
  • Look-ahead of materials and approvals needed in the next 6 weeks
  • Cash: certified work, escrow releases, collections from buyers

Biggest schedule risks

  • Authority approvals in months 2–4
  • Long-lead items: lifts, chillers, façade (ordered by month 8)
  • Labour availability during peak finishing (months 20–26)

Want this for your own project?

Tell us about it and the Projects team will prepare yours.

Illustrative sample for a fictional project. Figures are indicative only and are not an offer, valuation or professional advice. Your own study uses your plot, your market data and current rates, confirmed by Mizo's team.